Almost always. A typical central Indiana install is a one-day job, and the verification retest runs 48 hours once the fan is on. The schedule-critical steps are agreeing on scope quickly and getting the install date locked.
More detail
Work the calendar backward. The retest result should be in hand before the final walkthrough, the retest needs the fan running first, and the install needs a signed scope before that, so the real deadline is the week the parties agree on who fixes and who pays. What compresses well: the install itself, and quoting, which can usually happen from the inspection photos plus one site visit. What does not compress: a disagreement held until the response deadline. Bring the written quote into the repair negotiation rather than a vague credit, because a specific number settles faster than an estimate range. Share the closing date on the first call and the whole sequence gets built around it. The home sale walkthrough shows the timeline with dates on it.